A company has established 5 pounds of Material M at $2 per pound as the standard for the material in its Product A. The company has just produced 1,000 units of this product, using 5,200 pounds of Material M that cost $9,880.The direct materials price variance is:
A. $520 unfavorable.
B. $400 unfavorable.
C. $120 favorable.
D. $520 favorable.
E. $400 favorable.

Answer

This answer is hidden. It contains 98 characters.