Question

A company has two products: A1 and B2. It uses activity-based costing and has prepared the following analysis showing budgeted cost and activity for each of its three activity cost pools:


Budgeted Activity
Activity Cost Pool Budgeted Cost
Product A1

Product B2
Activity 1 $48,000 1,200 4,800
Activity 2 $63,000 2,240 4,760
Activity 3 $80,000 7,200 800

Annual production and sales level of Product A1 is 8,480 units, and the annual production and sales level of Product B2 is 22,310 units. What is the approximate overhead cost per unit of Product B2 under activity-based costing?
A. $8.00
B. $9.00
C. $10.00
D. $12.00
E. $4.00

Answer

This answer is hidden. It contains 800 characters.