Question

A company made the following expenditures in connection with the construction of its
new building:


Architects fees for the new building $ 12,000
Cash paid for land and run-down building on the land 300,000
Removal of old building 18,000
Salvage from sale of old building materials 4,000
Construction survey to site the new building 1,500
Legal fees for title search 3,000
Excavation for basement construction 25,000
Machinery purchased for operations 100,000
Storage charges on machinery because building was not ready when machinery was delivered 900
Freight on machinery purchased 1,600
Hauling charges to deliver machinery from storage to new building 300
Construction costs of new building 1,000,000
Landscaping 20,000
Installation of machinery 2,500

Prepare a schedule showing the amounts to be recorded as land, buildings, and machinery.

Answer

This answer is hidden. It contains 429 characters.