Question

A company must perform a maintenance project consisting of seven activities. The activities, their predecessors and their respective time estimates are presented below:

Using the Single Time Estimate CPM procedure, which activities make up the critical path?
A. A, B, D, F, G
B. A, C, E, F, G
C. A, C, B, F, E
D. A, D, E
E. None of the above