Question

A company must perform a maintenance project consisting of seven activities. The activities, their predecessors and their respective time estimates are presented below:

Using the Single Time Estimate CPM procedure, what is the Latest Finish Time for the last activity in this project (i.e., the total time to complete the project)?
A. 9 days
B. 10 days
C. 11 days
D. 12 days
E. 13 days