Question

A company wants to determine its reorder point (R). Demand is variable and they want to build a safety stock into R. If the average daily demand is 12, the lead time is 5 days, the desired "z" value is 1.96 and the standard deviation of usage during lead time is 3, which of the following is the desired value of R?
A. About 6
B. About 16
C. About 61
D. About 66
E. About 79

Answer

This answer is hidden. It contains 1 characters.