Question

A job has 10 days of processing time left to do before completion and today is the 5th day of the month. If the job is due on the 15th day of the month, what is its critical ratio?
A. 3
B. 2
C. 1
D. 0.8
E. 0.8

Answer

This answer is hidden. It contains 1 characters.