A job was budgeted to require 3 hours of labor per unit at $8.00 per hour. The job consisted of 8,000 units and was completed in 22,000 hours at a total labor cost of $198,000. What is the total labor cost variance?
A. $2,000 unfavorable.
B. $3,000 unfavorable.
C. $6,000 unfavorable.
D. $8,000 unfavorable.
E. $9,000 unfavorable.

Answer

This answer is hidden. It contains 108 characters.