Question

A listing of immediate predecessor activities is important information in a single time estimate CPM analysis for which of the following reasons?
A. It specifies the relationships in the CPM network of activities
B. It provides useful timing information
C. It includes cost information
D. It is the probability information required in the final step of CPM
E. None of the above