A manufacturer of automobile engines is designing a new Kanban system for engine #321. The demand for #321 is 75 parts per day, and the container can hold 8 parts at a time. The total processing and waiting time is 3 days. The manager wants a safety factor (α) of 2 or 200 percent. How many Kanbans are required in this system?

a. 85

b. 90

c. 100

d. 115