Question

A network has been crashed to the point where all activities are critical. Additional crashing:

A) is unnecessary.

B) is impossible.

C) is prohibitively expensive.

D) may require crashing multiple tasks simultaneously.

E) can be done, but all critical tasks must be reduced in duration.

Answer

This answer is hidden. It contains 17 characters.