Question

A product design team is preparing to build a new doohickey. A doohickey consists of one A module, one B module, and one C module. There are different versions of these modules available in the company's design library. For example, there are two choices for A: A1 is .99 reliable, while A2 is .975 reliable. The table below details the choices available, along with the cost of each choice.


Module variation Reliability Cost, each
A1 .99 $17
A2 .975 $10
B1 .995 $4
B2 .992 $3
C1 .98 $2
C2 .90 $0.50
C3 .60 $0.25

Help the design team by selecting the least costly version of a doohickey that has system reliability of at least .96. Draw a schematic of your finished design.

Answer

This answer is hidden. It contains 715 characters.