Question

A project being analyzed by PERT has 38 activities, 16 of which are on the critical path. If the estimated time along the critical path is 90 days with a project variance of 25, the probability that the project will be completed in 88 days or less is

A) 0.0228

B) 0.3446

C) 0.6554

D) 0.9772

E) 18