Question

A project being analyzed by PERT has 60 activities, 13 of which are on the critical path. If the estimated time along the critical path is 214 days with a project variance of 100, what is the probability that the project will take 224 days or more to complete?

A) near zero

B) 0.0126

C) 0.1587

D) 0.8413

E) 2.14