Question

A project manager is interested in crashing a project with variable activity times. Which of the following tools should he/she employ?

A) PERT

B) CPM

C) Gantt Chart

D) either PERT or CPM

E) PERT, CPM, or a Gantt chart are fine.

Answer

This answer is hidden. It contains 17 characters.