A proposed project has cash flows of $2,000, $?, $1,750, and $1,250 at the end of Years 1 to 4. The discount rate is 7.2 percent and the present value of the four cash flows is $6,669.25. What is the value of the Year 2 cash flow?

A) $2,450

B) $2,750

C) $2,500

D) $2,250

E) $2,800