Question

A technique that uses optimistic, pessimistic, and realistic time to calculate the expected time for a particular task best defines:
A) Gantt.
B) Computer Aided Software Engineering (CASE).
C) Program Evaluation Review Technique (PERT).
D) flowcharting.
E) Unified Modeling Language (UML).