Question

Activity 4-5 in a network diagram has an optimistic time estimate of five days, a most likely time estimate of seven days, and a pessimistic time estimate of 10 days. Its expected time (in days) is approximately:

A. 5.

B. 6.

C. 7.

D. 8.

E. 9.

Answer

This answer is hidden. It contains 36 characters.