Question

Activity R on a CPM network has predecessors M and N, and has successor S. R has duration 5. N's late finish is 18, while M's is 20. S's late start is 14. Which of the following is definitely true?

A) R is critical and has zero slack.

B) R has no slack but is not critical.

C) The set of times cannot all be possible.

D) N is a critical activity.

E) S is a critical activity.

Answer

This answer is hidden. It contains 21 characters.