An activity on a PERT network has these time estimates: optimistic = 2, most likely = 5, and pessimistic = 10. Its expected time is

A) 5.00

B) 5.33

C) 5.67

D) 17.00

E) none of these

Answer

This answer is hidden. It contains 1 characters.