Question

Ann Chovies, owner of the Perfect Pasta Pizza Parlor, uses 20 pounds of pepperoni each day in preparing pizzas. Order costs for pepperoni are $10.00 per order, and carrying costs are 4 cents per pound per day. Lead time for each order is three days, and the pepperoni itself costs $3.00 per pound. What is the economic order quantity for pepperoni?

A. 20 pounds

B. 40 pounds

C. 60 pounds

D. 80 pounds

E. 100 pounds