Question

Assume there are five jobs (i.e., A, B, C, D and E) that need to be sequenced in a production schedule. The remaining operating time necessary for completion of job A is 3 days (i.e., job A will take 3 more days to complete), B will take 9 days, C will take 6 days, D will take 5 days and E will take 8 days. In what order will these jobs be scheduled if using the SOT priority rule for job sequencing?
A. A-B-D-E-C
B. A-D-C-E-B
C. D-C-A-B-E
D. B-E-C-D-A
E. E-D-A-B-C

Answer

This answer is hidden. It contains 1 characters.