Average completion (flow) time for a schedule sequence at a work center is:

A. the sum of processing time divided by the number of jobs.

B. the sum of jobs' flow times divided by the number of jobs.

C. overall flow time divided by total processing time.

D. total processing time plus total late time divided by number of jobs.

E. the sum of flow time plus total late time divided by number of jobs.

Answer

This answer is hidden. It contains 55 characters.