Beta Inc. can produce a unit of Zed for the following costs:
Direct material $ 10
Direct labor 20
Overhead 50
Total costs per unit $80



An outside supplier offers to provide Beta with all the Zed units it needs at $58 per unit. If Beta buys from the supplier, it will still incur 40% of its overhead. Beta should:
A. Buy Zed since the relevant cost to make it is $60.
B. Make Zed since the relevant cost to make it is $60.
C. Buy Zed since the relevant cost to make it is $80.
D. Make Zed since the relevant cost to make it is $30.
E. Buy Zed since the relevant cost to make it is $30.

Answer