Question

Better Houses, Inc. has been contracted to build an addition on the Joyners' house. It built half of the addition and then unexpectedly announced that it was not going to finish the job. Such a desertion of work is called:

A. a constructive breach of contract.

B. substantial performance.

C. abandonment of contractual obligations.

D. a repudiation of contract.

Answer

This answer is hidden. It contains 183 characters.