Question

Changes to the baseline project plan might be motivated by:
A) a slipped completion date of an activity.
B) a bungled activity that must be redone.
C) the identification of a new activity that becomes evident later in the project.
D) an unforeseen change in personnel due to sickness, resignation, or termination.
E) all of the above.