Claymore Corp. has the following information about its standards and production activity for September. The controllable variance is:
Actual total factory overhead incurred "u00a6"u00a6"u00a6"u00a6"u00a6"u00a6"u00a6"u00a6 $28,175
Standard factory overhead:
Variable overhead "u00a6"u00a6"u00a6"u00a6"u00a6"u00a6"u00a6"u00a6"u00a6"u00a6"u00a6"u00a6"u00a6"u00a6"u00a6. $3.10 per unit produced
Fixed overhead
($12,000/6,000 estimated units to be produced) $2 per unit
Actual units produced "u00a6"u00a6"u00a6"u00a6"u00a6"u00a6"u00a6"u00a6"u00a6"u00a6"u00a6"u00a6."u00a6"u00a6. 4,800 units



A.$1,295U.
B.$1,295F.
C.$2,400U.
D.$2,400F.
E.$3,695U.

Answer