Question

Completion time (from start to finish) of a building remodeling project is normally distributed with a mean of 200 work-days and a standard deviation of 10 work-days. The probability that the project will be completed within 185 work-days is ______.
a) 0.0668
b) 0.4332
c) 0.5000
d) 0.9332
e) 0.9950