Question

Completion time (from start to finish) of a building remodeling project is normally distributed with a mean of 200 work-days and a standard deviation of 10 work-days. To be 99% sure that we will not be late in completing the project, we should request a completion time of _______ work-days.
a) 211
b) 207
c) 223
d) 200
e) 250