Consider the bill of material for Product J and the data given in the following table. The gross requirements for J are 200 units in week 6 and 250 units in week 8. Develop the MRP tables for each item for an 8-week planning period. Use the lot-for-lot lot-sizing rule.


Item Lead Time Quantity on Hand Scheduled receipts
J 1 0
K 2 20 30 in week 2
L 2 0
M 1 20 10 in week 1