Question

Demand for dishwasher water pumps is 8 per day. The standard deviation of demand is 3 per day, and the order lead time is four days. The service level is 95%. What should the reorder point be?

A) about 18

B) about 24

C) about 32

D) about 38

E) more than 40

Answer

This answer is hidden. It contains 26 characters.