Dressler Tech is considering a 3-year project with a discount rate of 15 percent, an initial cost of $95,000, projected sales of 1,300 units on the last day of each year, and a cash flow per unit of $38. The project can be abandoned following the sales on the last day of Year 2 at which time the project's assets could be sold for an estimated $40,000. What is the net present value of this project at Time 0 if the sales forecast for Year 3 of the project is revised such that there is a 50/50 chance that the sales will be either 1,100 or 1,500 units a year?

A) −$13,474

B) −$2,526

C) $19,172

D) $8,192

E) $18,887

Answer

This answer is hidden. It contains 356 characters.