During the Iteration Planning Game's steering phase:
A) programmers write the code for a feature, test it, and if it works, they integrate the feature into the product being developed.
B) business creates a Story Card for something it wants the new system to do.
C) programmers convert Story Cards into Task Cards.
D) business sees how the development process is progressing and works with Development to adjust the plan accordingly.
E) programmers accept responsibility for tasks and balance their workloads.