Question

Ehrmann Data Systems is considering a project that has the following cash flow and WACC data. What is the project's MIRR? Note that a project's projected MIRR can be less than the WACC (and even negative), in which case it will be rejected.

WACC: 9.75%

Year 0 1 2 3

Cash flows -$1,000 $450 $450 $450

a. 14.11%

b. 15.52%

c. 15.81%

d. 10.72%

e. 17.22%

Answer