Eight jobs have been sequenced at a single work center. Total processing time for the eight jobs is 34 hours and total flow time for the sequence is 85 hours. For this schedule, utilization is __________ and average jobs in the system is __________.

A) 100 percent; 10.625

B) low; .0941

C) 0.400 or 40 percent; 2.5

D) 0.235 or 23.5 percent; 4.25

E) maximized; minimized