Question

Eva, the owner of Eva's Second Time Around Wedding Dresses, currently has five dresses to be altered, shown in the order in which they arrived:



If Eva uses the shortest processing time first priority rule to schedule these jobs, what will be the average number of jobs in her shop today?

A. 2 jobs

B. 2.33 jobs

C. 2.4 jobs

D. 2.67 jobs

E. 3 jobs

Answer

This answer is hidden. It contains 65 characters.