Question

Fairview Industries is preparing its aggregate plan for the second half of the year. The table below contains monthly demand estimates and working days per month. Complete the table by computing total demand, demand per day (for each month), and the average requirement (in units per day) over the six-month planning horizon. Prepare a graph of forecast demand and level production, by months, for the planning period. Label your graph carefully.


Month Expected Demand Production Days Demand per Day
July 18,000 20
August 21,000 23
September 17,500 21
October 12,500 21
November 12,000 20
December 13,500 21
TOTAL

Answer

This answer is hidden. It contains 223 characters.