Fogelin Promotional Services uses a job order system for costing and billing promotional services for dance and ballet performances. Fogelin has 4 public relations specialists, plus an office staff. At the beginning of 2012, Fogelin estimated the total cost of salaries and benefits for the public relations specialists at $403,200, and a total of 7,200 billable hours for the year. All remaining office and administrative costs were estimated at $676,800.

In June, Fogelin signed a contract for a Russian ballet performance. They estimated it would require 34 hours of specialist time. What is the total cost estimate for this contract?

A) $1,904

B) $5,100

C) $3,196

D) $4,906