For an activity in a Single Time Estimate CPM analysis, the Early Finish time is 8 and the Late Finish time is 10. Which of the following statements is true?
A. The Late Start Time is 4
B. The Early Start Time is 4
C. The slack for this activity is 2
D. The duration of this activity is 2
E. The activity is on the critical path

Answer

This answer is hidden. It contains 1 characters.