For an activity in a Single Time Estimate CPM analysis the Early Finish time is 20 and the Late Finish time is 20. Which of the following statements is true?
A. The activity's late start must happen before its early start
B. The activity is on the critical path
C. The slack for this activity is 20
D. The duration of this activity is zero
E. The duration of this activity is 20