Question

Fred's Fabrication has the following aggregate demand requirements and other data for the upcoming four quarters.


Quarter Demand Previous quarter's output 800 units
1 700 Beginning inventory 0 units
2 900 Stockout cost $100 per unit
3 1200 Inventory holding cost $10 per unit at end of quarter
4 600 Hiring workers $20 per unit
Laying off workers $40 per unit
Subcontracting cost $200 per unit
Unit cost $100 per unit

Which of the following production plans is better: Plan Achase demand by hiring and layoffs; Plan Bpure level strategy, or Plan C700 level with the remainder by subcontracting?