Question

Given the critical path below, calculate the following:

a. The crash cost per unit time savings for each activity.

b. The maximum total crash time savings and cost.

c. The maximum total time-savings with a $3000 budget.


Activity Normal Time Normal Cost Crash Duration Crash Cost
A 8 days $8,000 7 days $12,000
B 5 days $2,000 3 days $10,000
C 10 days $9,000 9 days $12,000

Answer

This answer is hidden. It contains 222 characters.