Question

Given the following chart of jobs assigned with Johnson's rule, suppose that all the jobs (A, B, C, etc) could be evenly divided into two tasks (such as A1 and A2, B1 and B2, etc). Suppose job D is split into two equivalently sized sections, D1 and D2, each with a body work time of 1.5 hours and a paint time of 2 hours (D1 and D2 sum to 3 hours of body work and 4 hours of paint which is equivalent to D). How much is makespan reduced by this splitting of D?


Answer