Question

Given the project within the table below calculate

a. The critical path

b. The minimum project duration

c. The amount of slack for each activity


Activity Duration (hours) Immediate Predecessors
A 4 None
B 3 None
C 10 None
D 7 B,C
E 1 D
F 1 E
G 5 A,F