Question

Given the project within the table below, calculate the following:

a. The critical path

b. The minimum project duration

c. The amount of slack for each activity


Activity Duration (hours) Immediate Predecessors
A 4 None
B 3 None
C 10 None
D 7 B,C
E 1 D
F 1 E
G 5 A,F

Answer

This answer is hidden. It contains 209 characters.