Question

GL Plastics spent $1,200 last week repairing a machine. This week the company is trying to decide if the machine could be better utilized if they assigned it a proposed project. When analyzing the proposed project, the $1,200 should be treated as which type of cost?

A) Opportunity

B) Fixed

C) Incremental

D) Erosion

E) Sunk