Gold Company uses a plantwide overhead rate with machine hours as the allocation base. Use the following information to solve for the amount of machine hours estimated per unit of product RST.
Direct material cost per unit of RST $15
Total estimated manufacturing overhead $300,000
Total cost per unit of RST $80
Total estimated machine hours 150,000 MH
Direct labor cost per unit of RST $23

A. 21 MH per unit of RST.
B. 2 MH per unit of RST.
C. 20 MH per unit of RST.
D. 37.5 MH per unit of RST.
E. 38 MH per unit of RST.

Answer

This answer is hidden. It contains 188 characters.