Granite Company purchased a machine costing $120,000, terms 1/10, n/30. The machine was shipped FOB shipping point and freight charges were $2,000. The machine requires special mounting and wiring connections costing $10,000. When installing the machine, $1,300 in damages occurred. Compute the cost recorded for this machine assuming Granite paid within the discount period.
A.$129,800.
B.$132,100.
C.$130,800.
D.$118,800.
E.$120,100.