Question

Identify in which listed project phase each following project activity would normally occur. Use each phase once only.
a. Conceptual planning
b. Schematic design
c. Design development
d. Construction documents
e. Bidding and award
1 _____ Evaluate and finalize mechanical and electrical systems
2 _____ Review and recommend trade contracts with owner
3 _____ Describe owner's objectives
4 _____ Analyze alternative schemes and conduct engineering analysis
5 _____Prequalify trade contractors

Answer

This answer is hidden. It contains 34 characters.