Question

If an assignment problem consists of 6 workers and 7 projects:

A) one worker will not get a project assignment.

B) one worker will be assigned two projects.

C) each worker will contribute work toward the seventh project.

D) one project will not get a worker assigned.

E) The problem cannot be solved by assignment method.